FG Needs N920 Billion To Complete On-Going Road Projects – Minister

The Minister of Works, Mike Onolemeihmen has said that N920 billion will be required to complete Federal road projects that are on-going across the federation. The … Continue reading FG Needs N920 Billion To Complete On-Going Road Projects – Minister


The Minister of Works, Mike Onolemeihmen has said that N920 billion will be required to complete Federal road projects that are on-going across the federation.
The Minister, who briefed journalists after the weekly Federal Executive Council (FEC) meeting, said, if government were to depend solely on its annual budget of N190 billion, “it will take another eight years before the projects can be completed.”

Mr. Onolememen, spoke alongside the Minister of Information, Labaran Maku, hinting at a plan of a loan to cover the shortfall.

“To ensure timely completion of all the projects, a multilateral approach was under way as well as a Public Private Partnership (PPP) scheme that will add about 6,000 kilometres of road nationwide is being explored,” he said.

The minister said in the past twelve years, the federal works authorities spent N1.397 trillion on road works in the six zones of the country. Breaking it down to details, he said: the federal ministry works had completed 31 road projects in the north central zones, covering 1,054 kilometers at the total sum of N262.3 billion.

The north east has a total of 30 ongoing projects covering a total of about 1,461 kilometer at the contract sum of N332.9 billion. The northwest has a total of 23 ongoing projects covering a total of about 1,028 kilometer at the contract sum of N255.5 billion.

The south east has a total of 40 ongoing projects covering a total of about 978 kilometer at the contract sum of N149.6 billion. The south south has a total of 34 ongoing projects covering a total of about 876 kilometer at the contract sum of N159.4 billion. The south west has a total of 37 ongoing projects covering a total of about 1,230 kilometer at the contract sum of N236.9 billion.

“Out of this total portfolio size of ongoing project that has been put at N1.397 trillion, a total of about N523.6 billion has been certified and only about N475.5 billion has been paid, leaving a balance of about N921.4 billion of that portfolio.

“Which means that cumulatively unto the time that portfolio is completed we will be requiring about N921.4 billion to complete all the over 195 ongoing projects in the country” the minister said.

For the last year alone, Mr. Onolememen said his ministry received a total capital budgetary provision of about N143.5 billion, and paid out N101 billion. He added that the ministry received a marginal N85.5 billion allocation from the Subsidy Reinvestment and Empowerment Programme, SURE-P, through which six projects were currently being funded including the Lokoja- Abaji-Abuja Road.

He commended President Goodluck Jonathan, saying “in the last two years, the road sector has received direct attention from Mr. President,”
The Minister was complemented by his junior minister, Bashiru Yuguda, who disclosed that the ministry no longer paid contractors on presentation of certificate but on completion of a section of the road project.

“This is what we have done to make sure we get value for our money” Mr. Yuguda said.

The Information Minister, Labaran Maku, described the 2012 performance report of the ministry as “heartwarming” hinting that the presidency was happy with it, and that “this nation can be sure that the federal ministry of works is moving ahead to deliver major roads in the country.”